How to use this checklist
- Cracking, deformation, broken welds, loose fasteners, leakage or unexpected movement is found.
- Equipment has suffered impact, overload, collision, dropped load or abnormal operation.
- A workshop wants to know what information to gather before proposing a repair.
- An engineer or OEM needs a remote first-pass evidence package before attending site.
- Authorising continued operation of damaged equipment without a competent risk decision.
- Selecting an NDT method without discussing the defect, material and inspection purpose.
- Grinding out cracks or preparing a weld repair before the failure evidence is documented.
- Replacing a detailed inspection plan, engineering assessment or statutory notification process.
Stop and escalate when
These conditions deserve an explicit competent-person decision rather than being treated as routine checklist gaps.
Damage affects a primary load path, lifting point, pressure boundary, steering, braking or other safety-critical function.
Cracking is growing, deformation is active, leakage is worsening or the asset condition is unstable.
A component has fractured, separated, buckled or experienced a significant overload or impact event.
The proposed temporary control depends on an unverified assumption about remaining capacity.
Personnel are considering grinding, drilling, heating, straightening or welding before the evidence is recorded and the repair basis is established.
Working checklist
Your assessment is stored in this browser. Assign an explicit outcome, record the evidence behind it, and capture actions for every gap or unclear item.
Identify the asset and assessment basis
0 of 45 items have an explicit screening outcome.
1. Make the area safe and preserve evidence
Control immediate risk first, then protect the evidence needed to understand the event.
Add measurement, evidence or notes
Add measurement, evidence or notes
Add measurement, evidence or notes
Add measurement, evidence or notes
Add measurement, evidence or notes
Add measurement, evidence or notes
Add measurement, evidence or notes
2. Identify the asset and exact damage location
The assessment must be tied to a specific machine, component and location.
Add measurement, evidence or notes
Add measurement, evidence or notes
Add measurement, evidence or notes
Add measurement, evidence or notes
Add measurement, evidence or notes
Add measurement, evidence or notes
Add measurement, evidence or notes
3. Build a complete photo and measurement record
A useful evidence set moves from context to detail and always gives the viewer scale and orientation.
Add measurement, evidence or notes
Add measurement, evidence or notes
Add measurement, evidence or notes
Add measurement, evidence or notes
Add measurement, evidence or notes
Add measurement, evidence or notes
Add measurement, evidence or notes
Add measurement, evidence or notes
4. Record operating history and the event
The same visible crack can imply very different causes depending on duty, sequence and recent events.
Add measurement, evidence or notes
Add measurement, evidence or notes
Add measurement, evidence or notes
Add measurement, evidence or notes
Add measurement, evidence or notes
Add measurement, evidence or notes
Add measurement, evidence or notes
Add measurement, evidence or notes
5. Check repair and recurrence history
Previous work often changes both the likely failure mechanism and the repair options now available.
Add measurement, evidence or notes
Add measurement, evidence or notes
Add measurement, evidence or notes
Add measurement, evidence or notes
Add measurement, evidence or notes
Add measurement, evidence or notes
Add measurement, evidence or notes
6. Prepare the inspection and engineering handover
The objective is not to diagnose the failure from a checklist. It is to give the next competent person reliable inputs.
Add measurement, evidence or notes
Add measurement, evidence or notes
Add measurement, evidence or notes
Add measurement, evidence or notes
Add measurement, evidence or notes
Add measurement, evidence or notes
Add measurement, evidence or notes
Add measurement, evidence or notes
Record the final screening context
Note operating restrictions, missing documents, work orders, competent-person decisions or assumptions that affect the result.
Minimum useful attachment pack
The checklist is most useful when the evidence can travel with the request.
Five questions before you call it complete
Common gaps and weak evidence
The crack is visible, but the engineer cannot tell what component it is in, how it is supported or where load enters the detail.
Grinding or gouging removes fracture features, crack origin information and the as-found condition.
The assessment sees today's defect but misses repeated failures, abnormal events and earlier repairs.
Different teams assume the equipment is quarantined, restricted or approved for use without one controlled decision.